Friday, April 26, 2013

ALERT! RSM-Coto de Caza Alternate Routes this weekend


 Posted by CotoBlogzz

Rancho Santa Margiarita, CA - The contractor for Southern California Edison will be working in the City to install the final slurry seal resurfacing for the SCE Consejo Project this weekend,  The aim of the project is to improve power reliability in the city

 On Saturday, work will start at 3:00 a.m. and all lanes will be open by 2:00 p.m.  On Sunday, work will begin at 6:00 a.m., and all lanes will be open by 2:00 p.m..  

Crews  will be working on the following streets:  El Paseo, Santa Margarita Parkway, and La Promesa/Coto de Caza Drive.  

Please consider alternate routes during these times.  See below for  a tentative schedule.

.
 
 
 

No comments: